Weekly Update for the Lowson Blvd Improvement Project 2/19/24

  • Crews completed paving the final lift of asphalt on SE 10th St between Old Dixie Hwy to Federal.
  • Crews began grading and placing top soil along the South side of SE 10th St between Old Dixie Hwy to Federal in preparation for placement of sod.

Upcoming Week of February 19th

  • President’s Day, Monday, Feb 19th – No work is scheduled for the observed holiday.
  • Continue grading the remaining areas in the parkways and swales on SE 10th St between Federal to Old Dixie Hwy with top soil in preparation for sod.
  • Crews will be performing a rolling straight edge test throughout the project on the final lift of asphalt that has recently been completed.
  • Installation of new guard rail at Lowson Blvd and Dover Rd at the Canal.
  • Installation of the final handrails at the Pedestrian Bridge is expected in March.

Upcoming Construction at the intersection of SW 10th St/Lowson Blvd and Congress Ave.

  • New ADA ramps and sidewalks are planned to be installed at the intersection at all four corners with new Pedestrian Signals.
  • Night Time Work – Milling and Paving of the intersection will take place at Night. As date approaches, a new update will be posted.