• Weekly Update for the Lowson Blvd Improvement Project 9/22/23:
    • Crews continued placing sod along SW 10th St. between SW 10th Ave. to SW 8th Ave. and also began work between SW 4th Ave. to SW 2nd Ave.
    • Crews poured the concrete aprons around drainage inlets along both sides of SW 10th St. between SW 8th Ave. to 95 Bridge.
    • Crews continued pouring new concrete curb & gutters and shared use path along the north side of SW 10th St. between SW 2nd Ave. to Swinton Ave.  
    • Drainage work also continued along the south side of SE 10th St. between Old Dixie Hwy to SE 4th Ave.
  • Upcoming Week of Sept 25th:
    • Continue with installation of new curbs and shared use path along the north side of SW 10th St. between SW 2nd Ave. to Swinton Ave.
    • Begin removal and framing up for new curb & gutters and sidewalks at the SE corner of SW 10th St. and SW 4th Ave. with new ADA ramps.
    • Continue with installation of new drainage along the south side of SE 10th St. between Old Dixie Hwy to SE 4th Ave.
    • Begin adjusting frames in pavement areas along SW10th St./Lowson Blvd. for final lift of asphalt west of SW 10th Ave.
    • Begin installing the sidewalk along the south side of Lowson Blvd. near Dover Rd. at the Canal.
  • Motorists can expect minor delays traveling thru the Work Zone Areas

Comments are disabled