- Weekly Update for the Lowson Blvd Improvement Project 7/21/23:
- Work continued along SW 10th St between SW 4th Ave to SW 8th Ave in the Road Closed Section with crews framing up and pouring concrete curb & gutters, Sidewalks and Driveways. Finished grading the new rock base and paved the first lift of Asphalt between SW 4th Ave to SW 6th Ave. Workers also began placing the sod in the new parkways along the North and South sides of SW 10th St. The first lift of asphalt is now complete on the SW 10th St section between SW 4th Ave to SW 8th Ave.
- Crews also paved the temporary asphalt shared use path along the south side of SW 10th St near Pine Grove Elementary School.
- Crews also continued working along SW 10th St between SW 10th Ave to SW 15th Ave working on the South Side of the roadway for the new concrete curb & gutters and Shared Use Path.
- Upcoming Week of July 24th:
- SW 10th Street is closed to Thru Traffic during the reconstruction of the roadway between SW 4th Ave to SW 8th Ave.
- The roadway closure is expected to last from June 5th thru August 4th while Pine Grove Elementary is out of session for the summer.
- Detour Route is set up to detour traffic to the North on SW 4th Ave and SW 8th Ave and to use SW 4th Street to the East and West.
- Work will continue framing up and pouring the last remaining concrete sidewalks and driveways, as well as placing sod in the remaining parkways.
- Work at the Pedestrian Bridges will continue on the West side for the new gravity walls for the approach slabs.
- Work along SW 10th St between SW 10th Ave to SW 15th Ave will continue along the South side for installing new concrete curb & gutters and Shared Use Path.
- Motorists can expect minor delays traveling thru the Work Zone Areas
July 21, 2023