• Weekly Update
    • Crews continued with framing up and pouring new concrete Type F Curbs and Shared-Use Path along both the North and South sides of Lowson Blvd between the Canal Bridge towards Congress Blvd.
    • Drainage work also continued along Lowson Blvd/SW 10th St between SW 16th Ave to SW 11th Ave installing new drainage structures and adjusting existing structures for the new improvements.
  • Upcoming Week of February 13th:
    • Continue with framing up and pouring concrete for Shared Use Path along the North and South sides of Lowson Blvd between the Canal Bridge towards Congress.
    • Continue with the new Drainage Improvements along SW 10th St/Lowson Blvd between SW 17th Ave to SW 11th Ave.
    • Pavement Milling along Lowson to scheduled to begin next week also between the Canal Bridge to just west of Congress Blvd. 

 Motorists can expect minor delays traveling thru the Work Zone Areas.