Weekly Update for the Lowson Blvd Improvement Project 2/3/23

  • Crews continued with framing up and pouring new concrete Type F Curbs along the North side of Lowson Blvd between the Canal Bridge towards Congress, as well as pouring new sections of the concrete Shared Use Path.
  • Crews placed sod along Lowson Blvd between Dover Rd to Homewood.
  • Drainage work continued along Lowson Blvd/SW 10th St between SW 16th Ave to SW 11th Ave at installing new drainage structures and pipe.

 Upcoming Week of February 6 thru February 10

  • Continue with framing up and pouring concrete for the new Type F Curbs and Shared Use Path along the North and South sides of Lowson Blvd between the Canal Bridge towards Congress.
  • Continue with the new Drainage Improvements along SW 10th St/Lowson Blvd between SW 16th Ave to SW 11th Ave. 
  • Pavement Milling along Lowson scheduled to begin next week also between the Canal Bridge to just west of Congress Blvd. 

 Motorists can expect minor delays traveling thru the Work Zone Areas.