- Weekly Update for the Lowson Blvd Improvement Project 1/20/23
- Crews continued with framing up and pouring new concrete Type F Curb along the North side of Lowson Blvd between the Canal Bridge towards Congress.
- Crews also began framing up and pouring the new concrete shared use path on the North Side of Lowson Blvd between the Canal Bridge towards Congress.
- Crews also began laying out and grading for the shared use path along the south side of Lowson Blvd from the Canal Bridge to the East.
- Upcoming Week of January 23rd thru January 27th:
- Continue with framing up and pouring concrete for the new Type F Curbs and Shared Use Path along the North side of Lowson Blvd between the Canal Bridge towards Congress.
- Begin framing up and pouring the concrete Shared Use Path along the South side of Lowson Blvd between the Canal Bridge towards Congress.
- Drainage Improvements will be taking place along SW10th St between SW17th Ave to SW10th Ave.
- Motorists can expect minor delays traveling thru the Work Zone Areas.