• Project Update for the Week of December 19th:
      • The contractor poured the remaining sections of the Concrete Shared Use path between Dover Rd to the Canal East of Homewood.
      • Crews began drainage work along Lowson Blvd/SW 10th St just East of Congress on the North Side.
      • Crews began framing up and pouring the new concrete curb & gutters along the North side of Lowson Blvd west of SW 20th Ct.
      • Crews also placed the 1st lift of asphalt at driveway returns along Lowson Blvd between Camino Rd to the Canal East of Homewood Blvd.
      • Friday, December 23rd – No work will be scheduled for Christmas Weekend.
    • Upcoming Week of December 26th:
      • Monday, December 26th – No work will be scheduled today for the Christmas Holiday Weekend.
      • Continue with curb installation along the North side of Lowson Blvd West of SW 20th Ct.
      • Continue drainage installation along SW 10th St near SW 8th Ave
      • Continue placing asphalt along Lowson Blvd between Dover Rd to Homewood Blvd to correct the new profile of the roadway.
      • Upcoming Monday, January 2nd – No work will be scheduled for the New Year’s Day Holiday.
    • Motorists can continue to expect minor delays traveling thru the Work Zone Area.