Weekly Update for the Lowson Blvd Improvement Project
-
- Project Update for the Week of November 14th:
- Contractor reset all the MOT and devices after Tropical Storm Nicole.
- Crews began excavation to install S-400 near SW 10th St and SW 8th Ave and discovered a utility cable conflict that needed to be relocated.
- Crews also continued installing 18” concrete pipe between S-211 to S-214 along the North side of Lowson Blvd near SW 21st Terrace.
- Sod also continued to be placed along Lowson Blvd for the graded swales and parkways between Homewood Blvd to the East.
- More sections of the Concrete Shared Use path were also poured mid-week along the South side of Lowson Blvd, West of Homewood Blvd.
- Upcoming Week of November 21st:
- Continue installing the 18” concrete pipe between S-211 to S-214 and install structure S-207.
- Thanksgiving Holiday – No work will be scheduled during the Thanksgiving holiday and will resume on November 28th.
- Motorists can continue to expect minor delays traveling thru the Work Zone Area.
- Project Update for the Week of November 14th: