- Project Update for the Week of September 19th:
- Crews completed installing the 18” pipe between structures S105 to S106 across Lowson Blvd and installed the new drainage inlet S106 in the south parkway.
- Crews also continued with grading and shaping the swales/ditches along Lowson Blvd between Camino Rd to Homewood Blvd.
- Upcoming Week of September 26th:
- Install new drainage structure S111 along the North side of Lowson Blvd just East of Del Aire Ave.
- Begin grading areas where the new drainage work has been completed and get ready for framing and pouring the Concrete Shared-Use path on both the North and South sides of Lowson Blvd between Dover Rd to Homewood Blvd.
- Continue with grading of the parkways swales/ditches will also continue along both side of Lowson Blvd between Dover Rd to Homewood Blvd.
- Project Update for the Week of September 19th:
Motorists can continue to expect minor delays traveling thru the Work Zone Area.