• Project Update for the Week of September 12th
      • Crews completed installing the 18” French drain pipe between structures S104 to S105 and also set the new drainage inlet S105.
      • Crews also continued with grading and shaping the swales/ditches along the North & South side of Lowson Blvd between Homewood Blvd to the Canal East of Homewood.
    • Upcoming Week of September 19th
      • Finish installing the frame and grate to new drainage structure S105.
      • Begin installing the new drainage pipe between S105 to S106 across Lowson Blvd.
      • Grading of the parkways swales/ditches will also continue along both side of Lowson Blvd between Homewood Blvd to the Canal Bridge East of Homewood.
    • Motorists can continue to expect minor delays traveling thru the Work Zone Area.