- Crews continued paving the final lift of asphalt along SW 10th St between SW 4th Ave to Swinton.
- Paving for the Final Lift on SE 10th St between Federal to Old Dixie Hwy has started.
- Concrete Sidewalks along the south side of SE 10th St between Old Dixie Hwy to Federal Hwy is now complete.
- Installation of new Street Signs throughout the project is now complete.
Upcoming Week of February 5th
- Finish paving the final lift of Asphalt on SE 10th St between Federal Hwy to Old Dixie Hwy.
- Begin grading the remaining areas in the parkways and swales on SE 10th St for placement of sod.
- The Contractor will begin doing some pavement repairs to the Asphalt along SW 10th St and also on Lowson Blvd just East of Homewood.
- Installation of new guard rail at Lowson Blvd and Dover Rd at the Canal.
- Installation of the final handrails at the Pedestrian Bridge is expected in March.
Upcoming Construction at the intersection of SW10th St/Lowson Blvd and Congress Ave
- New ADA ramps and sidewalks are planned to be installed at the intersection at all four corners with new Pedestrian Signals.
- Night Time Work – Milling and Paving of the intersection will take place at Night. As the date approaches, an update will be posted.