Weekly Update for the Lowson Blvd Improvement Project 1/5/2024

  • Crews finished pouring the new concrete sidewalk approaches for the new Pedestrian Bridges.
  • Crews added new Curbs at the NE and NW corners at Lowson Blvd and Homewood.
  • Crews began paving the final lift of asphalt on Lowson Blvd between Dover Rd to the Pedestrian Bridge.
  • Drainage work began at SE 10th St and Old Dixie Hwy.

Upcoming Week of January 8th

  • Continue paving the final lift of asphalt on Lowson Blvd between the Pedestrian Bridge to Congress Ave.
  • Continue with new drainage structures and inlets at SE 10th St and Old Dixie Hwy.
  • Continue adding new Concrete Curbs and Sidewalks along the south side of SE 10th St between Old Dixie Hwy to SE 2nd Ave.