Weekly Update for the Lowson Blvd Improvement Project 1/19/24
- Crews continued paving the final lift of asphalt along SW 10th St between I-95 Bridge to SW 8th Ave.
- Crews continued installing new curbs and sidewalks at the intersection of SE 10th St and Old Dixie Hwy.
- Installation of new Street Signs started along Lowson Blvd between Congress to Dover Rd and on SW 10th St between Congress to SW 8th Ave.
Upcoming Week of January 22nd
- Begin paving the final lift of asphalt on SW 10th St between SW 4th Ave to Swinton Ave.
- Continue installation of Curbs and Sidewalks along the South side of SE 10th St between Old Dixie Hwy to SE 3rd Ave.
- Continue adding new Street Signs along Lowson Blvd between Homewood Blvd to Congress.
- Installation of new guard rail at Lowson Blvd and Dover Rd at the Canal.