• Weekly Update for the Lowson Blvd Improvement Project 12/22/23:
    • Crews finished pouring the new concrete curbs and sidewalks along the north side of SE 10th St between Old Dixie Hwy to SE 4th Ave.
    • Crews continued paving asphalt between the I-95 Bridge to SW 10th Ave for the final lift.
    • The new concrete bridge deck was poured at the Pedestrian Bridge on Lowson Blvd between Congress and Homewood Blvd.
    • Crews also began pouring the new concrete sidewalk approaches to the Pedestrian Bridges.
  • Upcoming Week of December 25th:
    • No work is scheduled on Christmas Day, Dec 25th and Tuesday, Dec 26th. Work will resume on Wednesday, Dec 27th – Friday, Dec 29th.
    • No paving is scheduled for next week during the Christmas – New Year’s break.
    • Crews will continue to grade and pour the new concrete sidewalks for the Pedestrian Bridge approaches.
    • Final lift of paving will resume after New Year’s on SW 10th St between I-95 Bridge to SW 10th Ave.