Weekly Update for the Lowson Blvd Improvement Project 12/1/23
- Crews completed the new concrete Shared Use Path along the South side of SE 10th St between SE 3rd Ave to Federal Hwy.
- Crews continued with installing new drainage pipe and structures on SE 10th St between SE 3rd Ave to Dixie Hwy.
Upcoming Week of December 4th
- Continue with installation of new drainage pipe and structures along SE 10th St between SE 2nd Ave to Old Dixie Hwy.
- Continue with installation of new concrete shared use path along the south side of SE 10th St between SE 3rd Ave to Old Dixie Hwy.
- Install new Guard Rail on the south side of Lowson Blvd near Dover Rd.
Pedestrian Bridge Update
- Delivery and installation of the new Pedestrian Bridge is expected mid next week. This work will continue into the following week as crews assemble and set the new Pedestrian Bridge on the abutments.
- Please note that during installation of the new Pedestrian Bridge, Day Time Road Closure will be in place while they have a crane onsite to place the new bridge. Posted Detours will be in place to detour motorists south on both Congress and on Homewood to use Linton Ave.