• Weekly Update for the Lowson Blvd Improvement Project 10/13/23:
    • Installation of the new Concrete Curb & Gutters and Sidewalks along SW 10th St between SW 4th Ave to Swinton Ave is nearing 90% completion.
    • Milling and Paving the 1st Lift of Asphalt on SW 10th St between SW 4th Ave to Swinton Ave began.
    • Crews continued grading parkways for Sod along SW 10th St between SW 4th Ave and SW 2nd Ave.
    • Installation of the new Sidewalk and Curb along the South side of Lowson Blvd at Dover Rd is complete.
    • Crews also continued installing the remaining drainage structures along the South side of SW 10th St between SW 11th Ave to SW 12th Ave.
  • Upcoming Week of Oct 16th:
    • Finish milling and paving the 1st lift of Asphalt along SW 10th St between SW 4th Ave to Swinton Ave.
    • Finish remaining drainage structures along south side of SW 10th St between SW 11th Ave to SW 12th Ave.
    • Begin the installation of new Curb & Gutters along the North side of SE 10th St between SE 2nd Ave to SE 4th Ave.
    • Continue grading parkways and swales along SW 10th St between SW 4th Ave to Swinton Ave and placing sod.
  • Motorists can expect minor delays traveling thru the Work Zone Areas