• Weekly Update for the Lowson Blvd Improvement Project 7/28/23:
    • Work continued along SW 10th St between SW 4th Ave to SW 8th Ave in the Road Closed Section with pouring the remaining concrete sidewalks and driveways. Crews also continued with placing sod in the parkways.
    • Framing for the Gravity Walls at the Pedestrian Bridge began this week on the West side of the Pedestrian Bridge.
    • Crews also continued working along SW 10th St between SW 10th Ave to SW 15th Ave working on the South Side of the roadway for the new concrete curb & gutters and Shared Use Path.
    • Work also began along SW 10th St between SW 8th Ave to SW 10th Ave at milling the pavement and paving the first lift of asphalt.
    • Crews will be working Saturday 7/29/23 on SW 10th St near SW 12th Ave.
  • Upcoming Week of July 31st:
    • SW 10th Street is closed to Thru Traffic during the reconstruction of the roadway between SW 4th Ave to SW 8th Ave and is scheduled to reopen on Friday August 4th.
    • The final lift of Asphalt is scheduled to begin next for the School area between SW 4th Ave to SW 8th Ave, followed by placing the new Pavement Markings.
    • Work at the Pedestrian Bridges will continue on the West side for the new gravity walls for the approach slabs.
    • Work along SW 10th St between SW 10th Ave to SW 15th Ave will continue along the South side for installing new concrete curb & gutters and Shared Use Path.
  • Motorists can expect minor delays traveling thru the Work Zone Areas