- Weekly Update for the Lowson Blvd Improvement Project 7/14/23:
- Crews began installing new Handrails along the Shared Use Path along Lowson Blvd between Dover Rd to the Pedestrian Bridge just East of Homewood Blvd.
- Work continued along SW 10th St between SW 4th Ave to SW 8th Ave in the Road Closed Section with crews framing up and pouring concrete curb & gutters, Sidewalks and Driveways. Excavation for the new sub-base continued along with placing the new base rock. The first lift of Asphalt was also placed between SW 6th Ave to SW 8th Ave.
- Crews also was working along SW 10th St between SW 10th Ave to SW 15th Ave working on the South Side of the roadway for the new concrete curb & gutters and Shared Use Path.
- Crews will be working this Saturday, 7/15/23 in the SW 10th Ave Road Closed section with grading the new rock base and getting the last section ready for the 1st lift of Asphalt.
- Upcoming Week of July 17th:
- SW 10th Street is closed to Thru Traffic during the reconstruction of the roadway between SW 4th Ave to SW 8th Ave.
- The roadway closure is expected to last from June 5th thru August 4th while Pine Grove Elementary is out of session for the summer.
- Detour Route is set up to detour traffic to the North on SW 4th Ave and SW 8th Ave and to use SW 4th Street to the East and West.
- Crews will continue with grading the remaining area of Rock Base and getting the last section ready to pave the 1st lift of asphalt. Crews will also be grading the parkways and getting ready to place sod.
- Work at the Pedestrian Bridges will continue on the West side for the new gravity walls for the approach slabs.
- Work along SW 10th St between SW 10th Ave to SW 15th Ave will continue along the South side for installing new concrete curb & gutters and Shared Use Path.
- Motorists can expect minor delays traveling thru the Work Zone Areas