- Weekly Update for the Lowson Blvd Improvement Project 6/30/23
- Excavation began at the Pedestrian Bridges on the west side for the gravity walls for the approach slabs.
- Work continued along SW 10th St between SW 4th Ave to SW 8th Ave in the Road Closed Section with crews installing new drainage structures and pipe, framing up and pouring new concrete curbs and sidewalks and also excavating and placing base rock for the new roadway.
- Crews will be working this Saturday, 7/1/23 in the SW 10th Ave Road Closed section.
- Upcoming Week of July 3rd, 2023:
- SW 10th Street is closed to Thru Traffic during the roadway reconstruction between SW 4th Ave to SW 8th Ave.
- The roadway closure is expected to last from June 5th thru August 4th while Pine Grove Elementary is out of session for the summer.
- Detour Route is set up to detour traffic to the North on SW 4th Ave and SW 8th Ave and to use SW 4th Street to the East and West.
- Crews continue with excavation for the new roadway rock base, installation of new concrete curb & gutters and Sidewalks/Driveways.
- Work at the Pedestrian Bridges will continue on the West side for the new gravity walls for the approach slabs.
- Pedestrian Signal work at SW 10th St and SW 10th Ave is scheduled.
- HOLIDAY: 4th of July – No work is scheduled on Tuesday, July 4th in observance of the Holiday.
- Motorists can expect minor delays traveling thru the Work Zone Areas