• Weekly Update for the Lowson Blvd Improvement Project 6/16/23
    • Crews finished framing up and setting rebar for the new concrete abutments which will support the new Pedestrian Bridges along Lowson Blvd at the Canal Bridge just West of Congress and also poured the concrete on Tuesday.
    • Crews began framing up and pouring concrete along the North Side of SW10th St between SW 4th Ave to Mango Dr to begin installation of the new concrete sidewalks.
  • Upcoming Week of 6/19/23
    • Continue with sidewalk improvements along the North side of SW 10th St between SW 4th Ave to Mango Dr.
    • Work will continue at the Pedestrian Bridge with pouring concrete for the remaining sections of the abutments.
  • SW 10th Street Road Closure Update
    • SW 10th Street is closed to Thru Traffic during the reconstruction of the roadway between SW 4th Ave to SW 8th Ave. This work will include removal of the exiting roadway, installation of new road base and pavement, along with new Concrete curbs, Sidewalks and driveways.
    • The roadway closure is expected to last from June 5th  thru August 4th while Pine Grove Elementary is out of session for the summer.
    • Detour Route will be set up to detour traffic to the North on SW 4th Ave and SW 8th Ave and to use SW 4th Street to the East and West.
    • Crews continued with installing new drainage pipe and structures between SW 7th Ave to SW 8th Ave.
    • Crews began pouring concrete for the new Shared Use Path along the south side of SW 10th St.
    • Crews also began excavation for the new aggregate base for the new roadway.
    • Crews also installed new Watermain connections for Pine Elementary School at SW 6th Ave and SW 10th St.
  • Motorists can expect minor delays traveling thru the Work Zone Areas.