- Weekly Update for the Lowson Blvd Improvement Project 5/12/23:
- Work continued along SW 10th St between SW 10th Ave to the SFRTA Railroad with crews milling the pavement and placing the 1st lift of Asphalt.
- Drainage work at SW 10th St and SW 8th Ave was completed.
- Crews also were grading the parkways/swale areas along Lowson Blvd between Homewood Blvd to the Pedestrian Bridge.
- Upcoming Week of May 15th:
- Continue working along SW 10th St between SW 10th Ave to the SFRTA Railroad with milling the pavement and placing the 1st lift of asphalt.
- Finish grading the parkway/swales along Lowson Blvd between Homewood to Dover Road and begin placing sod.
- Begin Drainage work along SE 10th St between SE 2nd Ave to S. Dixie Hwy.
- Pedestrian Bridge on Lowson Blvd between Congress and Homewood Blvd
- Excavation for the new Pedestrian Bridge abutments/Bend Ends is scheduled to begin.
- Motorists can expect minor delays traveling thru the Work Zone Areas