• Weekly Update for the Lowson Blvd Improvement Project 5/12/23:
    • Work continued along SW 10th St between SW 10th Ave to the SFRTA Railroad with crews milling the pavement and placing the 1st lift of Asphalt.
    • Drainage work at SW 10th St and SW 8th Ave was completed.
    • Crews also were grading the parkways/swale areas along Lowson Blvd between Homewood Blvd to the Pedestrian Bridge.
  • Upcoming Week of May 15th:
    • Continue working along SW 10th St between SW 10th Ave to the SFRTA Railroad with milling the pavement and placing the 1st lift of asphalt.
    • Finish grading the parkway/swales along Lowson Blvd between Homewood to Dover Road and begin placing sod.
    • Begin Drainage work along SE 10th St between SE 2nd Ave to S. Dixie Hwy.
    • Pedestrian Bridge on Lowson Blvd between Congress and Homewood Blvd
      • Excavation for the new Pedestrian Bridge abutments/Bend Ends is scheduled to begin.
  • Motorists can expect minor delays traveling thru the Work Zone Areas