- Weekly Update for the Lowson Blvd Improvement Project 4/28/23
- Work continued along the North side of SW 10th St between SW 10th Ave to SW 16th Ave with crews grading and pouring concrete curbs, Shared Use Path/Sidewalks and installing drainage improvements.
- Crews also continued grading for the new shared use path along the south side of SW 10th St between SW 8th Ave to SW 10th Ave.
- Crews also were grading the parkways/swale areas along the South side of Lowson Blvd between Congress Ave to the Pedestrian Bridge.
- Upcoming Week of May 1st
- Continue working along SW 10th St between SW 17th Ave to SW 10th Ave with drainage improvements, Concrete Curb & Gutters and shared-use path/sidewalks on the North side.
- Continue working along SW 10th St between SW 8th Ave to SW 10th Ave on the south side and installing the new concrete shared use path.
- Finish grading the parkway/swales along Lowson Blvd between Homewood to Dover Road and begin placing sod.
- Pedestrian Bridge on Lowson Blvd between Congress and Homewood Blvd
- Installation of the final piles is to begin on Monday, May 1st and continue thru Friday, May 5th.
- Daytime Road Closures will be in place during Pile Driving Operations from 7am to 5pm.
- Detour will be posted and will detour traffic to the south to use Linton Blvd between Congress to Homewood Blvd.
- Motorists can expect minor delays traveling thru the Work Zone Areas