• Weekly Update for the Lowson Blvd Improvement Project 4/21/23
    • Work continued along the North side of SW 10th St between SW 8th Ave to SW 16th Ave with crews grading and pouring concrete for the new Sidewalks and Curb & Gutters, drainage improvements and adjusting existing fire hydrants.
    • Work also continued along SW 10th St on the North side, between S. Swinton Ave to SW 4th Ave working on installing new drainage structures and adjusting fire hydrants.
    • Crews also began grading for the new shared use path along the south side of SW 10th St between SW 8th Ave to SW 10th Ave.

 

  • Upcoming Week of April 24th
    • Continue working along SW 10th St between SW 17th Ave to SW 8th Ave with drainage improvements, Concrete Curb & Gutters and shared-use path/sidewalks.
    • Continue working along SW 10th St between SW 6th Ave to SW 8th Ave with installing new drainage structures.
    • Pedestrian Bridge on Lowson Blvd between Congress and Homewood Blvd
      • The next phase of installing the remaining piles is tentatively scheduled to begin the week of May 1st.
      • Daytime Road Closures will be in place during Pile Driving Operations from 7am to 5pm.
  • Motorists can expect minor delays traveling thru the Work Zone Areas