• Weekly Update for the Lowson Blvd Improvement Project 4/14/23:
    • Work continued along the North side of SW 10th St between SW 8th Ave to SW 16th Ave with crews grading and pouring concrete for the new Sidewalks and Curb & Gutters, drainage improvements and adjusting existing fire hydrants.
    • Work also continued along SW 10th St on the North side, between S. Swinton Ave to SW 4th Ave working on installing new drainage structures.
    • The 2nd of two Test Piles for the Pedestrian Bridge was completed on Wednesday.  
  • Upcoming Week of April 17th:
    • Continue working along SW 10th St between SW 17th Ave to SW 8th Ave with drainage improvements and new concrete sidewalks and curb & gutters and adjusting existing fire hydrants.
    • Continue working along SW 10th St between SW 6th Ave to SW 8th Ave with installing new drainage structures.
    • Pedestrian Bridge on Lowson Blvd between Congress and Homewood Blvd
      • The test piles have been completed. Once the production piles have been ordered, it will take about 3 weeks before the next phase of Pile Driving begins and daytime road closures will take place again.

 

  • Motorists can expect minor delays traveling thru the Work Zone Areas