• Weekly Update for the Lowson Blvd Improvement Project 2/24/23
    • Crews continued with framing up and pouring new concrete Shared-Use Path along both the North and South sides of Lowson Blvd between the Canal Bridge towards Congress Blvd.
    • Drainage work continued along Lowson Blvd/SW 10th St between SW 17th Ave to SW 10th Ave at installing new drainage structures and adjusting existing structures for the new improvements.
    • Asphalt paving crew began finished paving the driveway entrances along Lowson Blvd west of the Canal Bridge.
    • Construction work also started between Swinton Ave to SW 4th Ave, which will include new Curb & Gutters, Drainage improvements and concrete sidewalks.
  • Upcoming Week of February 27th :
    • Finish pouring the concrete Shared Use Path along the South sides of Lowson Blvd between the Canal Bridge towards Congress.
    • Continue with the Drainage Improvements along SW 10th St/Lowson Blvd between SW 17th Ave to SW 10th Ave.
    •  Begin removing and installing the new sidewalks along SW 10th St on the North Side between SW 17th Ave to SW 10th Ave.
    • Continue with roadway improvements along SW 10th St between Swinton Ave to SW 4th Ave.
  •  Motorists can expect minor delays traveling thru the Work Zone Areas.
  • Upcoming Public Outreach Meeting March 7th
    • Public Outreach Meeting for the New Pedestrian Bridge at the Canal will be held at 6pm to 7pm at the Swinton Operations Complex at 200 SW 6th St. in Delray Beach. Meeting will discuss the upcoming installation of the new Pedestrian Bridges at the Canal Bridge between Congress and Homewood Blvd.