• Weekly Update for the Lowson Blvd Improvement Project 1/6/23
    • Crews this week milled the existing pavement along Lowson Blvd between Dover Rd to the Canal just East of Homewood Blvd.
    • Paving the first list of asphalt and correcting the overbuild area also began today on Lowson Blvd between Dover Rd to Homewood Blvd.
    • Crews excavated and framed up for the new Concrete Curb & Gutters along the south side of road at Lowson Blvd and Dover Rd and will be pouring the concrete today.
  • Upcoming Week of January 9th – 13th
    • Crews will continue Monday with paving asphalt along Lowson Blvd between Dover Rd to the Canal just East of Homewood Blvd.
    • Drainage Improvements will be taking place along SW10th St between SW17th Ave to SW10th Ave.
    • Construction of the Shared Use path along Lowson Blvd between the Canal and Congress may also begin.
  • Motorists can expect minor delays traveling thru the Work Zone Area during the Paving Operations.