• Project Update for the Week of Dec 12th:
    • Crews continued with grading along the Shared Use Path along the south side of Lowson Blvd between Homewood Blvd to Dover Rd.
    • Installation of drainage structures along Lowson Blvd west of Congress was completed.
    • Excavation for the new Curb & Gutters along the North side of Lowson Blvd just west of SW 20th Ct was also completed.
    • Installation of the new drainage structures East of Congress on the North side of Lowson Blvd began.
  • Upcoming Week of December 19th:
    • Continue with grading the parkways along the shared use path for Sod installation along Lowson Blvd between Homewood Blvd to Dover Rd.
    • Begin pouring the new concrete curb & gutters along the North Side of Lowson Blvd just west of SW 20th Ct.
    • Continue with the new drainage structures along Lowson Blvd East of Congress.
  • Motorists can continue to expect minor delays traveling thru the Work Zone Area.

 