Weekly Update for the Lowson Blvd Improvement Project

    • Project Update for the Week of November 7th:
      • Due to Tropical Storm Nicole, the crew could not get much completed this week. Crews on Tuesday took time to secure the project and get ready for the storm.
    • Upcoming Week of November 14th:
      • Reinstall the MOT and signs that were taken down from the Tropical Storm.
      • Continue with grading the remaining sections of the Shared Use path along Lowson Blvd between Camino Rd to Homewood Blvd.
      • Continue with drainage improvements along Lowson Blvd between the Canal to SW 20th Ct. which includes completing the drainage run between S-214 to S-211.
      • Drainage work to begin between SW 8th Ave to SW 6th Ave adding new drainage structures along the North side of SW 10th St/Lowson Blvd.
    • Motorists can continue to expect minor delays traveling thru the Work Zone Area.