Weekly Update for the Lowson Blvd Improvement Project

    • Project Update for the Week of September 26th:
      • Due to the impact of Hurricane Ian, work was shut down this week.
    • Upcoming Week of October 3rd:
      • Re-install all MOT signage that was taken down during Hurricane Ian.
      • Install new drainage structure S111 along the North side of Lowson Blvd just East of Del Aire Ave.  
      • Begin grading areas where the new drainage work has been completed and get ready for framing and pouring the Concrete Shared-Use path on both the North and South sides of Lowson Blvd between Dover Rd to Homewood Blvd.
      • Continue with grading of the parkways swales/ditches will also continue along both side of Lowson Blvd between Dover Rd to Homewood Blvd.
    • Motorists can continue to expect minor delays traveling thru the Work Zone Area.