• Project Update for the Week of September 19th:
      • Crews completed installing the 18” pipe between structures S105 to S106 across Lowson Blvd and installed the new drainage inlet S106 in the south parkway.
      • Crews also continued with grading and shaping the swales/ditches along Lowson Blvd between Camino Rd to Homewood Blvd.
    • Upcoming Week of September 26th:
      • Install new drainage structure S111 along the North side of Lowson Blvd just East of Del Aire Ave.  
      • Begin grading areas where the new drainage work has been completed and get ready for framing and pouring the Concrete Shared-Use path on both the North and South sides of Lowson Blvd between Dover Rd to Homewood Blvd.
      • Continue with grading of the parkways swales/ditches will also continue along both side of Lowson Blvd between Dover Rd to Homewood Blvd.

Motorists can continue to expect minor delays traveling thru the Work Zone Area.

 